S can complete a work in 36 days b in 24 days.If both work together they will complete in how many days.

Answers

Answered by Anonymous
1
Hey there
Here is your answer...

☺☺☺☺❤☺☺☺☺
Attachments:
Answered by starmou14
0
The answer is 14 whole 2 by 5 days ..