Sachin can finish a piece of work in 24 days. he started the work but left after 6 days. His friend Mohit agreed to finish the work for him and took 9 days to complete the remaining work. find the number of days in which Mohit could finish the entire work alone.
the spamming answer is no appreciated. Thanking you.
Answers
Answered by
4
Answer:
12 days
Step-by-step explanation:
Given,
Sachin can finish a piece of work in 24 days.
Sachin=1/24 days
he started the work but left after 6 days.
he worked for 6/24 days=1/4 days
remaining work 1-1/4=3/4
3/4 work in days
we know,total work is always 1
3/4 work=9 days
1 work=x days
3/4*x=9
x=12 days