Sachin can finish a piece of work in 24 days.He started the work but left after 6 days.His friend Mohit agreed to finish the work for him and took 9 days to complete the remaining work.Find the number of days in which Mohit could have finished the entire work alone.
Answers
Answered by
0
12 days