Sakshi can designer saree in 25 days while smiriti can design it in 20 days if the both design the same saree together for 5 days and then sakshi leaves. in how many days Will Smriti finish remaining work?
Answers
Answered by
2
400/11 days is answer.
Attachments:
![](https://hi-static.z-dn.net/files/de6/3c9e5714412fd6d96e9d671e5afca4c2.jpg)
suryanshshukla33:
please mark me as brainleast
Answered by
0
Step-by-step explanation:
Time taken by Sakshi to design a saree : 25
Time taken by Smriti to design a saree : 20
sakshi's 1 day work : 1/25
smriti's 1 day work : 1/20
Both's 1 day work : 1/25 + 1/20
4+5/100 : 9/100
9/100*5 : 9/20 work has been done.
9/20-20 : 11/20*20 : 11 days