sanju can do a piece of work in 4 days and sumit can do it 6days. how long will they take if both sanju and sumit work together.
Answers
Answered by
15
Let total amount of the work be 'z',
amount of work which Sanju can do in a day be 'x' and amount of work which Sumit can do in a day be 'y'.
As per the question, Sanju can do a piece of work in 4 days>>4x=z____(1)
Also,it is given that Sumit takes 6days for same work >>6y=z____(2)
From(1),x=z/4
From(2),y=z/6
When both of them work together,
Number of days=Total work/amount of work they can do in a day
=z/(x+y)
=z/(10z/24)
=24/10=2.4days
Thus, they take 2.4days(2days and 9.6hours)to complete the work
Hope this helps you
amount of work which Sanju can do in a day be 'x' and amount of work which Sumit can do in a day be 'y'.
As per the question, Sanju can do a piece of work in 4 days>>4x=z____(1)
Also,it is given that Sumit takes 6days for same work >>6y=z____(2)
From(1),x=z/4
From(2),y=z/6
When both of them work together,
Number of days=Total work/amount of work they can do in a day
=z/(x+y)
=z/(10z/24)
=24/10=2.4days
Thus, they take 2.4days(2days and 9.6hours)to complete the work
Hope this helps you