Math, asked by ajitpurohit6, 9 months ago

Saurabh can complete a work in 18 hours while Vinod can complete the same work in 24 hours. How long will it take them together to complete the work if Saurabh is called away 2 hours before the completion of work, while Vinod continues with work​

Answers

Answered by MissKalliste
13

Answer:

\boxed{\frac{80}{7}}

Step-by-step explanation:

→ Let Vinod continues the work = x hours

→ So, now Saurabh can do the work = (x - 2) hours

→ Work done by Saurabh in 1 hour = 1/18

→ Then, work done by Saurabh in (x - 2) hours = x - 2/18

→ Work done by Vinod = x/24

→ Now, work done by both them together = x - 2/18 + x/24

Here, we can see that the whole work 1 is completed. So,

→ x - 2/18 + x/24 = 1

= 4x - 8 + 3x/72 = 1

Now, we will take 72 in the opposite side and multiply it with 1, as it was in division so when we will change it,it will be in the form of multiplication.

= 4x - 8 + 3x = 72

= 7x - 8 = 72

= 7x = 72 + 8

= 7x = 80

= x = 80/7

We can write it in the form of mixed fraction.

= x = 11 whole 3/7

\mathrm{\therefore They\:together\: finished\:the\:work\:in\:80/7 \:hours \:or \:11 \:whole \:3/7 \:hours.}

_________________________

Answered by Anonymous
21

\blue{\bold{\underline{\underline{Answer:}}}}

 \:\:

 \green{\underline \bold{Given :}}

 \:\:

  • Saurabh can complete a work in 18 hours

 \:\:

  • Vinod can complete the same work in 24 hours

 \:\:

 \red{\underline \bold{To \: Find:}}

 \:\:

How long will it take them together to complete the work if Saurabh is called away 2 hours before the completion of work, while Vinod continues with work

 \:\:

\large{\orange{\underline{\tt{Solution :-}}}}

 \:\:

Let Vinod continues the work = x hours

 \:\:

Saurabh can do the work = (x - 2)hours

[Saurabh is called away 2 hours before]

 \:\:

 \underline{\bold{\texttt{Work done in 1 hr.}}}

 \:\:

Saurabh in 1 hour =  \sf \dfrac { 1} { 18 }

 \:\:

Saurabh in (x - 2) hours =  \sf \dfrac { x - 2} { 18 }

 \:\:

Work done by Vinod =  \sf \dfrac { x } { 24 }

 \:\:

Now, work done by both them together =  \sf \dfrac { x - 2} { 18 } + \dfrac { x } { 24 }

 \:\:

Here, we can see that the whole work 1 is completed.

 \:\:

 \sf \longmapsto \dfrac { x - 2} { 18 } + \dfrac { x } { 24} = 1

 \:\:

 \sf \longmapsto \dfrac { 4x - 8 + 3x } { 72 } = 1

 \:\:

 \sf \longmapsto 4x - 8 + 3x = 72

 \:\:

 \sf \longmapsto 7x - 8 = 72

 \:\:

 \sf \longmapsto 7x = 72 + 8

 \:\:

 \sf \longmapsto 7x = 80

 \:\:

 \sf \longmapsto x = \dfrac { 80 } { 7}

 \:\:

 \bf \dashrightarrow x = 11 \dfrac { 3} { 7 }

 \:\:

\sf \therefore They\:together\: finished\:the\:work\:in \\ \\ \sf \dfrac { 80} { 7} \:hours \:or \:11\dfrac { 3} { 7} \:hours.

\rule{200}5

Similar questions