Sheetal can do a piece of work in 6 days and Raj can do the same work in 8 days. Both work for 2 days and Sheetal leaves. How long will Raj take to complete the remaining work ? wht is the ans​

Answers

Answered by soumyapandey13
0

Answer:

5 days

Step-by-step explanation:

hope it helps you bhaiya

Answered by srisaipoojitha9e2497
1

step by step explanation

sheetal can do a work in = 6days

sheetal, 1day work =1/6

Raj can do a work in = 8days

Raj, 1 day work =1/8

Both (sheetal + Raj) 1day work = 1/6 + 1/8

=7/12

so , the remaining work = 1- 7/12 = 12-7/12 = 5/12

Now

It is given that ,

sheetal can do a work in 6days

sheetal can do 5/12 work in = 6× 5/12 days

=5/2 days

1

= 2 -----days