Math, asked by kamakshi05, 10 months ago

Shri Ram can do 1/4th of work in 8 days in how many days he will do the whole work​

Answers

Answered by madhulachu
3

Answer:

in 8 days 1/4th work is done then to do whole work is 8×4=32 days

Answered by kunalkumarray2903
0

Answer:

SHREERAM CAN DO COMPLETE WORK IN 32 DAY.

Step-by-step explanation:

BECAUSE :

SHREE RAM CAN DO 1/4 th OF A WORK IN 8 DAYS .

THEN, SHREE RAM CAN DO WHOLE WORK IN 8×4 = 32 DAYS .

HOPE IT HELP YOUR