Six men can complete a work in 12 days. Two days later, 6 more men joined them.
How many days will they take to complete the remaining work?
Answers
Answer:
7 days
Step-by-step explanation:
6 men can complete a job in = 12 days.
If 6 men can complete a job in 12 days, thus the input =
6 × 12 = 72 man-days
In two days the work completed is 6 × 2 = 12 man-days of work.
Remaining work to be done = 72 - 12 = 60 man-days of work.
Thus if 6 more men are added, then the work force becomes 12 men strong.
Hence, the remaining work can be completed in -
60/ 12 = 5
= 5 man days
Thus, the total work will be completed in 2 + 5 or 7 days from the start or 5 days after the additional 6 men have joined.
Answer:
This is the simple way of solving the question and the remaining work will be completed by total workers is 5 days after 6 more men joined.
Step-by-step explanation:
Given:
6 men can completing a work in 12 days.
That means:
1 men will do a 1 work in a day.
So total works = =
works.
Work will be done by 6 men in 2 days is:
Hence work left
After two days 6 men join for the same work
So total men will be
Therefore remaining work will be done by 12 workers will be: