Math, asked by varshitha3116, 1 year ago

Six men can do a piece of work in 6 days. Two men can do the work in

Answers

Answered by leenayuktabajaj
0

Answer:

18 days

Step-by-step explanation:

Inverse Variation:

6 men - 6 days

2 men - x days

Therefore, x= 6*6/2= 18 days

Answer is 18. Hope it helps.

Answered by Anonymous
5

Solution:

No. of days taken by 6 men to do the work = 6

No. of days taken by 1 man to do the work = 6 x 6 = 36

No. of days taken by 2 men to do the work = 36/2

Answer = 18 days.