six persons can do a piece of work in 8 days .how long will it take 12 persons to do this piece of work
Answers
Answered by
2
Answer:
As it is in inverse proportion. So,
6×8=12×x
48=12x
48/12=x
4=x
So, 12 persons will take 4 days
Step-by-step explanation:
Mark it as the brainliest and follow me
Answered by
1
Answer:
If Six person had already completed the work then the 12 person will not need to complete that work.