Sixteen men can complete a work in twelve days. Twenty four children can complete the same work in 18 days. 12 men and 8 children started working and after eight days three more children joined them. How many days will they now take to complete the remaining work?
Answers
Answered by
16
Answer:
Step-by-step explanation:
Attachments:
Answered by
0
If they will take 4 more days, they will complete the remaining work.
Step-by-step explanation:
To find:
In how many days will they now take to complete the remaining work?
Solution:
Lets assume Men as "M" and children as "C" .
So as per the Question
16M 12 = 24C 18
=>
Total work= 16 9 12
Lets assume days required to complete remaining work = x days.
x=
= 4 days.
To know more:
45 men can complete a work in 16 days. six days after they started working, 30 more men joined them. how many days will they now take to complete the remaining work?
https://brainly.in/question/1282785
14 men can complete a work in 12 days 4 days after they started the work 2 more men joined them how many days will they work take to complete the remaining work
https://brainly.in/question/9133691
Similar questions