Math, asked by devyu7506, 11 months ago

Sixteen men can complete a work in twelve days. Twenty four children can complete the same work in 18 days. 12 men and 8 children started working and after eight days three more children joined them. How many days will they now take to complete the remaining work?

Answers

Answered by belikebullet
16

Answer:


Step-by-step explanation:


Attachments:
Answered by kingofself
0

If they will take 4 more days, they will complete the remaining work.

Step-by-step explanation:

To find:

In how many days will they now take to complete the remaining work?

Solution:

Lets assume Men as "M" and children as "C" .

So as per the Question

16M \times 12 = 24C \times 18

\frac{M}{C} = \frac{432}{192}

=> \frac{M}{C} = \frac{9}{4}

Total work= 16 \times 9 \times 12

Lets assume days required to complete remaining work = x days.

\rightarrow {{(12 \times 9) + (8 \times 4)} \times 8} + {{(12 \times 9) + (11 \times 4)} \times x} = 16 \times 9 \times 12

x=\frac{608}{152}

= 4 days.

To know more:

45 men can complete a work in 16 days. six days after they started working, 30 more men joined them. how many days will they now take to complete the remaining work?

https://brainly.in/question/1282785

14 men can complete a work in 12 days 4 days after they started the work 2 more men joined them how many days will they work take to complete the remaining work

https://brainly.in/question/9133691

Similar questions