solve above question plz
Answers
Solution :
We have provided with the data that 12 men and 18 women can do a piece of work in 14 days then we need to find how much time 8 men and 16 women take to finish the work
*According to the Question ,*
12 men is equal to 18 women in work
Implies , One men can do 12/18 women work in one day
One men Work = 1.5 of women work --> (1)
*Total Amount of Work to be done by Women*
⇒ 18 * 14
⇒ 252
From Equation (1)
⇒ 12 women + 16 women will take time
⇒ 28 women will take time
Finding the time
Time = (Work done\Number of Women)
Substituting the Value in the formula ,
⇒ (252/28)
⇒ 9 days
Answer:
Step-by-step explanation:
Total Amount of Work to be done by Women
→ 18 × 14
→ 252
From Equation (1)
12 women + 16 women will take time
→ 28 women will take time
Finding the time
Time = (Work done Number of Women)
Substituting the Value in the formula,
→ (252/28)
→ 9 days