Sujitha one day work=1/4
Ranju one day work=1/3
Both=1/4 +1/3
=3+4/12
=7/12
Ranju one day work=1/3
Both=1/4 +1/3
=3+4/12
=7/12
Answered by
0
Let, the total work be 'x'.
So, Sujita does in a day
= 1/4 part of the work.
= 1/4 * x = x/4.
Again, Ranju does in a day
= 1/3 part of the work.
= 1/3 * x = x/3.
Thus, in a day, if they work together, they will do work
= x/3 + x/4
= (4x + 3x) /12
= 7x/12.
Thus, if they work together in a day, they will do work
= 7x/12.
= 7/12 * x
= 7/12 part of the work.
Hope this helps,.