Solve this problem guys
Attachments:
Answers
Answered by
0
Answer:
15 days
Step-by-step explanation:
a+b+c=4 days
work in 1 day = 1/4
days taken by a = 12
days taken by b = 10
work in one day by a and b = 1/12+1/10
work in one day by c= 1/12+1/10+c = 1/4
= c = 1/4-11/60
= c = 4/60
days take by c = 60/4 = 15
PLS MARK ME AS BRAINLIEST PLSSSS
Similar questions