Math, asked by Monakumari7378, 6 months ago

SOLVED EN
if 36 men can finish a piece of work in 25 days, how many days will 15 men take
to de
25 days.​

Answers

Answered by ankitgamerx68
6

Step-by-step explanation:

60 days. We have to use inverse variation (36×25)÷15 =12×5 =60 If you like it then click thanks and the brainliest answer.

Mark me as a brainlist