Some men can complete a work in 40 days.
If there were more men to do the work then
the same work would be finished in
25 days. How many men were at the
beginning?
Answers
Answered by
1
Day is indirectly variated with workers.
When day decreases, the workers increases.
DW=k ( k is a variation constant )
k =40x
D'W'=k
25w = 40x
x= 0.625w
you have to give the number of workers once to have another as a result
if you are satisfied plz inform me