Math, asked by alikhansadath622, 11 months ago

Someone help me out with this questions

Attachments:

Answers

Answered by erronblack
0

Days required by 10 men to construct a wall of 180m=3 days

Days required by 1 man = 180m/10=18days

Men required to build 300m in 5 days=300/5=60/18=33 men