Accountancy, asked by kittumadhad, 11 months ago

standard time of a product = 6 hours per unit
standard rate = ₹ 4 per hour
actual cost of production = 1500 units
actual hour taken = 7600 units idle time = 400 units ( in hours)
totals hours = 8000
Total labour cost announced to rupees 40000.
calculate labour variances. ​

Answers

Answered by anamkhurshid29
2

Total hours : 8,000

Total labour cost announced to Rs. 40,000. Calculate Labour Variance.

Hope this helps ❤️❤️❤️

❤️