Sunil and Anil makes a wall in 4 days. Sunil alone takes 6 days in completing the same wall. in how many days can Anil alone make the wall?
Answers
Answered by
13
Total days taken when Sunil and Anil work together = 4
Work done in 1 day = 1/4
Total days taken when Sunil alone works = 6
Work done in 1 day = 1/6
Work done by Anil in 1 day;
Solving it further:-
Total days taken when Anil alone works = 1/12
=》
Anonymous:
Nice program ✌
Answered by
19
Work done in a day when both Sunil and Amit work together = 1/4
Work done in a day when only Sunil work = 1/6 .
Work done by Anil a day =
Work done by both a day - Work done by Sunil a day
Hence he will do the work in 24/10 days .
#Be Brainly !!
Work done in a day when only Sunil work = 1/6 .
Work done by Anil a day =
Work done by both a day - Work done by Sunil a day
Hence he will do the work in 24/10 days .
#Be Brainly !!