Swati paid rupees 600 for 8 days work to a labour. If he works for 20 days, how much will a labour get?
Answers
Answered by
2
Answer:
I think 1500 rupees ...
Answered by
1
For 8 days = 600
For 1 day = 600 / 8
For 20 days = (600/8)*20 = 1500
For 20 days he will get 1500 rupees
For 1 day = 600 / 8
For 20 days = (600/8)*20 = 1500
For 20 days he will get 1500 rupees