Tell me a process to how to solve this problem
Attachments:

Answers
Answered by
0
Answer: it's has to done by the process of unitary method...
Answered by
1
Step-by-step explanation: Let the time taken by bullocks alone to complete the job be x days .
Now let the time taken by tractors alone to complete the task be y days .
Therefore , amount of work completed in one day by bullocks will be 1/x and by tractors be 1/y .
The amount of work done by bullocks and tractors by working together will be 1/8 .
The two equations formed will be ,
1/x + 1/y = 1/8
And , 1/2x + 2/y = 1/5
Now you can solve these two linear equations in two variables to get your answer .
Please mark this explanation as the brainliest !