ten men can paint the second floor of a building in 3 days.How long would it take 6 men to do the same work?
Answers
Answered by
49
A n s w e r
G i v e n
- Ten men can paint the second floor of a building in 3 days
F i n d
- Days in which 6 men can complete the same work
S o l u t i o n
- Let 6 men can complete the work in 'd' days
As the work will remain in both the cases i.e with 10 men & 6 men hence we will calculate the total work required to complete the work
Case I [ With 10 men ]
➠ Total work = Men × Days
- Men = 10
- Days = 3
: ➜ Total work = 10 × 3
: ➜ Total work = 30 units
Case II [ With 6 men ]
➠ Total work = Men × Days
- Men = 6
- Days = d
: ➜ Total work = 6 × d
: ➜ Total work = 6d units
As discussed above the total work will remain same as in both cases as the work was same
Thus ,
: ➜ 30 = 6d
: ➜
: : ➨ d = 5 days
- Hence 6 men can complete the work in 5 days
hannahbuising1:
thx!!