ten mens take 4 days to complete
the work of tarving a road
How many days would 8 men take ?
Answers
Answered by
19
Answer:
NO OF MEN | 10 | 8
TIME | 4 | x
inverse proportion
10/4=8/x
10×4=8x
x=40/8
x=5
Answered by
1
This is your answer of the question.