Math, asked by rajsingh24, 1 year ago

\huge\red{QUESTION:}
Four persons started to do a work together. 'A' works only in starting two days after that B, C and D works alternately starting from B. Ratio of time taken by A, B, C and Dif they work alone is 4: 3: 2: 5. If the work is completed in 12 days then in how many days A and Ccan complete the work if they work together?​

Answers

Answered by Anonymous
2

Step-by-step explanation:.

A, B, C and D worked for 2 days together after that A leave and B, C and D worked alternatively for 10 days starting from B

∴ B worked for 4 days, C for 3 days, and D for 3 days.

Total days A worked = 2

Total days B worked = 4 + 2 = 6

Total days C worked = 3 + 2 = 5

Total days D worked = 3 + 2 = 5

Let, their alone time to complete the work is 4x, 3x, 2x and 5x

respectively.

∴ (2/4x) + (6/3x) + (5/2x) + (5/5x)= 1

⇒ (30+120+150+60) / 60 = 1

⇒ = 360/60 = 6

‘A’ can complete the work in 4 × 6 = 24 days

‘C’ can complete the work in 2 × 6 = 12 days

Required time = (12×24) / (12+24)

= (12×24)/36 = 8 days

hope it helps you

Answered by ʙʀᴀɪɴʟʏᴡɪᴛᴄh
4

Answer:

\huge{\fbox{\fbox{\bigstar{\mathfrak{\red{Answer}}}}}}

A, B, C and D worked for 2 days together after that A leave and B, C and D worked alternatively for 10 days starting from B

∴ B worked for 4 days, C for 3 days, and D for 3 days.

Total days A worked = 2

Total days B worked = 4 + 2 = 6

Total days C worked = 3 + 2 = 5

Total days D worked = 3 + 2 = 5

Let, their alone time to complete the work is 4x, 3x, 2x and 5x

respectively.

∴ (2/4x) + (6/3x) + (5/2x) + (5/5x)= 1

⇒ (30+120+150+60) / 60 = 1

⇒ = 360/60 = 6

‘A’ can complete the work in 4 × 6 = 24 days

‘C’ can complete the work in 2 × 6 = 12 days

Required time = (12×24) / (12+24)

= (12×24)/36 = 8 days

Similar questions