The Construction of house is completed by 40 labares in 60 days. The number of labores was reduced to 24 for more reasons but how many days to complete the Construction will take ?
Answers
Answered by
2
Answer:
100
because
60x40/24
= 100 days
Answered by
3
Step-by-step explanation:
40 labours do the work in 60 days
1 labour does the work in 60/40 days or 3/2 days
24 labours do the work in (3/2) x 24
= 1.5 × 24
= 36 days
Similar questions
Math,
3 hours ago
Math,
3 hours ago
Computer Science,
3 hours ago
Geography,
8 months ago
Math,
8 months ago