The expected project duration is determined by finding which path through the network?
(A) Shortest
(B) Longest
(C) Thinnest
(D) Thickest
Answers
Answered by
3
Explanation:
longest path b is the Wright answer
Answered by
2
Answer:
LONGEST PART IS USED TO DETERMINE THE EXPECTED PROJECTED DURATION
Explanation:
In project management, a critical path is the sequence of project network activities which add up to the longest overall duration, regardless if that longest duration has float or not. This determines the shortest time possible to complete the project. There can be 'total float' (unused time) within the critical path.