The Information about numbers of workers and number of days to complete a work is given in the following table. Complete the table.
NUMBER OF WORKERS 30 20 ......... 10 .........
DAYS 6 9 12 .......... 3
Answers
Answered by
24
Answer:
this is your answer I hope that it is useful to you