the method of the 3. 250 heads of people can dig a pond of size 50 meters long, 35 metres wide an 5.2 metres deep in 18 days by working 10 hours daily. Let's work out using th method of the Rule of Three how many days it will take for 300 people to dig pond of size 65 metres long, 40 metres wide and 5.6 metres deep by working hours daily
Answers
Answered by
1
Answer:
20 days is the right answer
Step-by-step explanation:
please mark as brainliest answer
Answered by
0
20 days will take for 300 people to dig pond