The people assigned to your project have high billable rates, and the project budget doesn't provide much of a buffer over your estimated total project cost. Fortunately, the project finish date has some wiggle room. Which measure of progress is most important to track in this situation? Select an answer:
Answers
Answered by
0
Answer:
where are the options???
Similar questions