Computer Science, asked by Anonymous, 6 months ago

The people assigned to your project have high billable rates, and the project budget doesn't provide much of a buffer over your estimated total project cost. Fortunately, the project finish date has some wiggle room. Which measure of progress is most important to track in this situation? Select an answer:

Answers

Answered by indiranandi256
0

Answer:

where are the options???

Similar questions