Math, asked by Catalinad3334, 11 months ago

The ratio of the efficiencies of a,b and c is 7:5:4. Working together, they can finish a work in 35 days, a and b work together for 28 days. The remaining work wikk be completed in days by c alone

Answers

Answered by amanyadav66
0

Answer:

Construct a right angle triangle ABC,whose hypotenuse AC=5.2cm and sum of remaining two sides is 7.2cm

https://brainly.in/question/13719812?utm_source=android&utm_medium=share&utm_campaign=question

Answered by FelisFelis
1

The time taken to complete remaining work is 56 days.

Step-by-step explanation:

Consider the provided information.

The ratio of the efficiencies of a,b and c is 7:5:4.

So the number of days to finish a work by a, b and c are \dfrac{x}{7} ,\dfrac{x}{5} \ and\ \dfrac{x}{4} respectively. Where x is the common factor.

Efficiency is inversely proportional to time taken.

If they can finish a work in 35 days.

\dfrac{7}{x} +\dfrac{5}{x} +\dfrac{4}{x} =\dfrac{1}{35}

x=16\times35

a and b work together for 28 days.

The work done by a and b in 28 days: 28\left(\dfrac{7}{x} +\dfrac{5}{x}\right) =\dfrac{12\times28}{x}

Substitute the value of x.

\dfrac{12\times28}{16\times35}=\dfrac{3}{5}

A and B completed \dfrac{3}{5} th of work now C need to complete only \dfrac{2}{5} th of work.

C can do the work in \frac{16\times35}{4}=140 days.

Hence, the time taken to complete remaining work is \frac{140\times2}{5} =56 days.

#Learn more

A and B can do a given piece of work in 8 days B and C can do the same work in 12 days and a b c complete it in 6 days in how many days can A and C finish it​

brainly.in/question/11917539

Similar questions