The ratio of the efficiencies of a,b and c is 7:5:4. Working together, they can finish a work in 35 days, a and b work together for 28 days. The remaining work wikk be completed in days by c alone
Answers
Answer:
Construct a right angle triangle ABC,whose hypotenuse AC=5.2cm and sum of remaining two sides is 7.2cm
https://brainly.in/question/13719812?utm_source=android&utm_medium=share&utm_campaign=question
The time taken to complete remaining work is 56 days.
Step-by-step explanation:
Consider the provided information.
The ratio of the efficiencies of a,b and c is 7:5:4.
So the number of days to finish a work by a, b and c are respectively. Where x is the common factor.
Efficiency is inversely proportional to time taken.
If they can finish a work in 35 days.
a and b work together for 28 days.
The work done by a and b in 28 days:
Substitute the value of x.
A and B completed th of work now C need to complete only th of work.
C can do the work in days.
Hence, the time taken to complete remaining work is days.
#Learn more
A and B can do a given piece of work in 8 days B and C can do the same work in 12 days and a b c complete it in 6 days in how many days can A and C finish it
brainly.in/question/11917539