Economy, asked by varunnair9531, 11 months ago

The relaxion time in such an operation, found from the tables is 10%. The worker rating of the operator of the machine was found to be 105. Other allowances include, 4% contingency and 2% interference allowance. Calculate the standard time and number of products that can be made in a shift.

Answers

Answered by silvershades54
0

Answer:

The relaxion time in such an operation, found from the tables is 10%. The worker rating of the operator of the machine was found to be 105. Other allowances include, 4% contingency and 2% interference allowance. Calculate the standard time and number of products that can be made

Answered by rosoni28
6

\huge \sf {\orange {\underline {\pink{\underline {❥︎A᭄ɴsᴡᴇʀ࿐ :−}}}}}

The ratings is used in conjunction with a timing study to level out actual time (observed time) taken by the worker under observation. This leads to a basic minute value (observed time/100*rating). This balances out fast and slow workers to get to a standard/average time