Math, asked by sanidhyapokhrai5977, 3 months ago

The standard hourly rate Is rs 1.40 the actual rate was rs 1.30 the labour rate variances was rs 600 favurable the actual hours (AH) were

Answers

Answered by amitnrw
0

Given : The standard hourly rate Is rs 1.40 the actual rate was rs 1.30 the labour rate variances was rs 600 favorable

To Find : the actual hours (AH)

A) 6000

B) 6400

 C) 1000

 D) 1500​

Solution:

Let say actual hours (AH)   =   X

actual rate was rs 1.30

=>  Actual Pay  = 1.3X

standard hourly rate Is rs 1.40

=> Standard Pay = 1.4X

variances was rs 600

=> 1.4X - 1.3X  = 600

=> 0.1X  =  600

=> X = 6000

actual hours (AH) were 6000

Learn More:

actual hours (AH) were

https://brainly.in/question/39984266

Similar questions