The time taken, t hours, to do a paint job is inversely proportional to the number of workers,N. Given that 9 workers take 20 hours to complete a job, find the time taken by 6 workers to complete the same job.
Answers
Answered by
0
Answer:
30 hours
Step-by-step explanation:
9 workers = 20 hours
1 worker = 9 * 20 = 180 hours
6 workers = 180 / 6 = 30 hours