thirty men can do a piece of work in 24days.In how many days can 20men do the work given that time spent per day is increased by one third of the previous time
Answers
Step-by-step explanation:
FOLLOW AND MARK AS BRAINLIEST
20 men do the work in 27 days if time spent per day is increased by one third of the previous time
Given:
30 Men can do a piece of work in 24 days.
Time spent per day is increased by one third of the previous time
To Find:
.In how many days now 20 men can complete the work
Solution:
Let say time spent every day is 3t hrs
(3t is assumed because one third of 3t will be t )
Work done by 1 man in 1 day = 3t man hrs
Work done by 30 men in 1 day = 30 * 3t = 90t man hrs
Work done by 30 men in 24 days =24* 90t = 2160t man hrs
time spent per day is increased by one third
Hence new time spent per day = 3t + 3t/3 = 4t hrs
Now Work done by 1 man in 1 day = 4t man hrs
Work done by 20 men in 1 day = 20 * 4t = 80t man hrs
Work done by 20 men in d days =d* 80t =80dt man hrs
(d is the number of days in which 20 men will complete the work)
Equate the man hrs and solve for d
80dt = 2160t
80d = 2160
8d = 216
d = 27
Hence 20 men do the work in 27 days if time spent per day is increased by one third of the previous time