Rhidhima Electronics Pvt Ltd is the main supplier for CASIO for electronics component. They manufacture keyboards and screens for graphing calculators at plant in Bangalore and Bhiwandi. The hourly production rates at each plant are given in the table. How many hours should each plant be operated to fill an order for exactly 4,000 keyboards and exactly 4,000 screen?


PLEASE ANSWER ONLY ANSWER

Attachments:

Answers

Answered by priyakumari12102006
0

Answer:

banglore should operate for 75 hours and bhiwadi for 50 hours

Step-by-step explanation:

we need 4000 keyboards and 4000 screens

can take any i am taking keyboards

so for banglore= 40*75=3000

and for bhiwadi=20*50=1000

total 4000 achieved

same for screens to be checked

Answered by amitnrw
1

Given  : hourly production rates at each plant

Plant      Keyboard      Screens

Bangalore   40             32

Bhiwandi     20             32

To Find : How many hours should each plant be operated to fill an order for exactly 4,000 keyboards and exactly 4,000 screen

Solution:

Assume that Bangalore plant for   x hours

and Bhiwandi Plant for y hours

40x  + 20y   =  4000     Eq1

32x  + 32y   =   4000

=>  x + y  = 125

=> y = 125 - x

Substitute in Eq1

=> 40x  + 20(125 - x)  = 4000

=> 40x + 2500 - 20x  = 4000

=> 20x  = 1500

=> x = 75

y = 125 - 75 = 50

Bangalore plant for 75 hours

and Bhiwandi Plant for 50 hours

Learn More:

27. The feasible solution for a LPP is shown in the following figure ...

brainly.in/question/22688248

Shalmali wants to invest ₹50,000 in saving certificates and PPF ...

brainly.in/question/6332423

solved by simplex method- Max Z= 3x1+2x2 s.t. 5x1+x2≤10 4x1+ ...

brainly.in/question/8809746

Similar questions