Three boys can do a piece of work in 2 days, how long will it take one boy to do it
Answers
Answered by
6
3 boys in 2 days.
1 boy in =3×2=6 days
1 boy in =3×2=6 days
Answered by
8
Hey friend! here is your answer ⏩
no of boys-3
days taken-2 days
let days be x done by one boy so,
indirect proportion
3×2=1×x
therefore, x=6
HOPE IT HELPS
@RASHI
no of boys-3
days taken-2 days
let days be x done by one boy so,
indirect proportion
3×2=1×x
therefore, x=6
HOPE IT HELPS
@RASHI