Three men and six boys can do a piece of work in two days. A man can do the work in 5 days less time than a boy. How many days can a man take to do the entire work
Answers
Answered by
0
3m + 6b = 2
So
6m + 12b = 1
And
A man takes X days
Boy takes X+5 days
6/m + 12/b = 1
6/x + 12/(x+5) = 1
After solving this you will get
X = 15 days