Three workers take 5 days to do a particular task. How many days will 6 workers take to do that very task.​

Answers

Answered by rabs6
17

Answer:

10 days

Step-by-step explanation:

days taken by 3 workers to complete a task = 5 days

days taken by 1 worker to complete a task = 5/3 days

daya taken by 6 worker to complete a task = 5/3 × 6

= 10 days