Time and Work - A, B, C Work on Alternate days
A, B, and C can do a piece of work in 20, 40 and 60 days respectively. When they work together on alternative days, then work completed how many days?

Answers

Answered by kausar2k2
1
They completed their work in 120 days.
Answered by navatharao30
0
lcm is 120
A can do 6 units
B can do 3units/day
c can do 2units/day
6 3 2 6 3 2 6 3 2 6 3 2 6 3 2 6 3 2 6 3  2  6 3 2 6 3 2 6 3 2 6 3 2 
inorder to finish 120 units we need 32 1/2 days