Time and Work!
P and Q together can do a piece of work in 10 days,Q and R can do the same work together in 12 days,while P and R can do together in 15 days. How long each will take to do it seperately?
Answers
Solution :
We have,
Adding,We get :
Now,
P's 1 day's work = (P + Q + R)'s 1 day's work - (Q + R)'s 1 day's work
So,P alone can complete the work in 24 days.
Q's 1 day's work = (P + Q + R)'s 1 day's work - (P + R)'s 1 day's work
So,Q alone can complete the work in 120/7 days.
R's 1 day's work = (P + Q + R)'s 1 day's work - (P + Q)'s 1 day's work
So,R alone can complete the work in 40 days.
Answer:
Therefore, P alone can complete the work in 24 days.
Therefore, Q alone can complete the work in 120 / 7 days.
Therefore, R alone can complete the work in 40 days.
Step-by-step explanation:
According to the Question,
(P + Q) can finish the work in 10 days.
So, (P + Q) can finish the work in 1 day = 1/10
(Q + R) can finish the work in 12 days.
So, (Q + R) can finish the work in 1 day = 1/12
(P + R) can finish the work in 15 days.
So, (P + R) can finish the work in 1 day = 1/15
On adding, we get:
2 × (P + Q + R)'s one day's work = 1/10 + 1/12 + 1/15
=> 6 + 5 + 4 / 60
=> 15 / 60 = 1/4
(P + Q + R)'s one day's work = 1 / 2×4
(P + Q + R)'s one day's work = 1/8
Now,
P's one day's work
=> (P + Q + R)'s one day's work - (Q + R) can finish the work in 1 day
=> 1/8 - 1/12
=> 3 - 2 / 24
=> 1 / 24
Therefore, P alone can complete the work in 24 days.
Now,
Q's one day's work
=> (P + Q + R)'s one day's work - (P + R) can finish the work in 1 day
=> 1/8 - 1/15
=> 15 - 8 / 120
=> 7 / 120
Therefore, Q alone can complete the work in 120 / 7 days.
Now,
R's one day's work
=> (P + Q + R)'s one day's work - (P + Q) can finish the work in 1 day
=> 1/8 - 1/10
=> 5 - 4 / 40
=> 1 / 40
Therefore, R alone can complete the work in 40 days.