Math, asked by indhuradithya2422, 1 year ago

to complete a work 28 person takes 36 days then 21 person how taken

Answers

Answered by noorjahan24
0
48 days to complete

noorjahan24: To complete the work of 21 person =28 *36/21, =48
noorjahan24: therefore to complete the work of 21 person 48 days are needed