Math, asked by 9881161521, 1 year ago

to complete a work ajay needs 5 days more than vijay. after 4days vijay left job then ajay complete the remaining job within 5 days then how much does each one take to complete the works?

Answers

Answered by ram071987
4

let bijay takes x days.

so Ajay takes (x + 5) days.

so bijays 1 day work = 1/x

Ajay's 1 day work = 1/(x + 5)

their 1 day work =

 \frac{1}{x}  +  \frac{1}{x + 5}  \\   \frac{x + 5 + x}{x(x + 5)}  \\  \frac{2x + 5}{x(x + 5)}

so their 4 days work

4( \frac{2x + 5}{x(x + 5)} ) \\  \frac{8x + 20}{ x(x + 5) }

remaining work =

1 -  \frac{8x + 20}{x (x + 5})  \\   \frac{ {x}^{2} + 5x - (8x + 20) }{x(x + 5)}   \\   \frac{ {x}^{2}  + 5x - 8x - 20}{x(x + 5)}  \\  \frac{ {x}^{2}  - 3x - 20}{x(x + 5)}

Ajay's 5 days work =

5 \times  \frac{1}{x + 5} \\  \frac{5}{x + 5}

since Ajay completes the remaining work in 5 days so,

 \frac{ {x}^{2} - 3x - 20 }{x(x + 5)}  =  \frac{5}{x + 5}  \\  {x}^{2}  - 3x - 20 = 5x \\  {x}^{2}  - 3x - 5x - 20 = 0 \\  {x}^{2}  - 8x - 20 = 0 \\  {x}^{2}  - 10x + 2x - 20 = 0 \\ x(x - 10) + 2(x - 10) = 0 \\ (x - 10)(x + 2) = 0 \\ if \: x - 10 = 0 \: then \: x = 10 \\ if \: x + 2 = 0 \: then \: x =  - 2

so x = 10 is correct.

therefore bijay takes 10 days.

Ajay takes 15 days.


ram071987: was it helpful?
Similar questions