to complete a work ajay needs 5 days more than vijay. after 4days vijay left job then ajay complete the remaining job within 5 days then how much does each one take to complete the works?
Answers
Answered by
4
let bijay takes x days.
so Ajay takes (x + 5) days.
so bijays 1 day work = 1/x
Ajay's 1 day work = 1/(x + 5)
their 1 day work =
so their 4 days work
remaining work =
Ajay's 5 days work =
since Ajay completes the remaining work in 5 days so,
so x = 10 is correct.
therefore bijay takes 10 days.
Ajay takes 15 days.
ram071987:
was it helpful?
Similar questions