to complete a work in 27 days 52 men are required how many men will be required to complete the same work in 36 days
Answers
Answered by
6
We know that,
D¹M¹ = D²M²
27 * 52 = 36 * M²
M² = 27*52/36
= 39.
So men required are 39
D¹M¹ = D²M²
27 * 52 = 36 * M²
M² = 27*52/36
= 39.
So men required are 39
Answered by
6
men's 1=52. men's 2=?
days 1=27. days2 =36
so ,
52*27/36
52*3/4
13*3
39......
hope it helps you pls give me a salamat and put it as a brain list please
days 1=27. days2 =36
so ,
52*27/36
52*3/4
13*3
39......
hope it helps you pls give me a salamat and put it as a brain list please