To complete the calendar schedule, the network is converted into ?
(A) Work-based network
(B) Node-based network
(C) Time-based network
(D) Schedule-based network
Answers
Answered by
1
Answer:
(C) Time-based network
Explanation:
hope its help
Answered by
0
Answer:
C is the correct answer