Total cost of work RS. 75,00,000 On 1st
April 2020 and 80% work done and 80% cash
received on 30th June 2020. What is the cash
received on 30th June.
Answer
A. RS 48,00,000
B. RS, 54,00,000
C. RS, 60,00,000
D. RS, 66,00,000
Answers
Answered by
0
Answer:
4800000
Explanation:
follow and thanks