Accountancy, asked by achalanandanwar, 2 months ago

Total cost of work RS. 75,00,000 On 1st
April 2020 and 80% work done and 80% cash
received on 30th June 2020. What is the cash
received on 30th June.
Answer
A. RS 48,00,000
B. RS, 54,00,000
C. RS, 60,00,000
D. RS, 66,00,000​

Answers

Answered by psubhaparamasivam
0

Answer:

4800000

Explanation:

follow and thanks