Computer Science, asked by dhalsmita45, 6 months ago

traveling sales man problem is applied on the group in
1.ADCBFA
2.AEBCDA
3.ABCDEA
4.non

Answers

Answered by dryash1009
0

Answer:

Explanation:

4.none

is the correct  

Answered by theaditisingh12
0

For example, consider the graph shown in figure on right side. A TSP tour in the graph is 1-2-4-3-1. The cost of the tour is 10+25+30+15 which is 80.

The problem is a famous NP hard problem. There is no polynomial time know solution for this problem.

Following are different solutions for the traveling salesman problem.

Naive Solution:

1) Consider city 1 as the starting and ending point.

2) Generate all (n-1)! Permutations of cities.

3) Calculate cost of every permutation and keep track of minimum cost permutation.

4) Return the permutation with minimum cost.

Time Complexity: Θ(n!)

Dynamic Programming:

Let the given set of vertices be {1, 2, 3, 4,….n}. Let us consider 1 as starting and ending point of output. For every other vertex i (other than 1), we find the minimum cost path with 1 as the starting point, i as the ending point and all vertices appearing exactly once. Let the cost of this path be cost(i), the cost of corresponding Cycle would be cost(i) + dist(i, 1) where dist(i, 1) is the distance from i to 1. Finally, we return the minimum of all [cost(i) + dist(i, 1)] values. This looks simple so far. Now the question is how to get cost(i)?

To calculate cost(i) using Dynamic Programming, we need to have some recursive relation in terms of sub-problems. Let us define a term C(S, i) be the cost of the minimum cost path visiting each vertex in set S exactly once, starting at 1 and ending at i.

We start with all subsets of size 2 and calculate C(S, i) for all subsets where S is the subset, then we calculate C(S, i) for all subsets S of size 3 and so on. Note that 1 must be present in every subset.

If size of S is 2, then S must be {1, i},

C(S, i) = dist(1, i)

Else if size of S is greater than 2.

C(S, i) = min { C(S-{i}, j) + dis(j, i)} where j belongs to S, j != i and j != 1.

For a set of size n, we consider n-2 subsets each of size n-1 such that all subsets don’t have nth in them.

Using the above recurrence relation, we can write dynamic programming based solution. There are at most O(n*2n) subproblems, and each one takes linear time to solve. The total running time is therefore O(n2*2n). The time complexity is much less than O(n!), but still exponential. Space required is also exponential. So this approach is also infeasible even for slightly higher number of vertices.

Similar questions