Twenty men were employed to do some work in a certain time . But one - third of the scheduled time was over , it was found that only one -quarter of the total work was completed . How many more men should now be employed to complete the work in three-fouths of the origionally scheduled time ?
Answers
Answer:
Step-by-step explanation:
Remaining Work =1-1/4=3/4
Remaining tym =3/4-1/3=5/12
(20*1/3)/(1/4) =(X*5/12)/3/4)
X=48
Extra=(48-20)=28 men
• Given:- Twenty men were employed to do some work in a certain time . But one - third of the scheduled time was over , it was found that only one -quarter of the total work was completed
• To find:- How many more men should now be employed to complete the work in three-fouths of the origionally scheduled time
• Solution:- According to the question, if the total work is 1, then remaining work = (1-1/4) = 3/4 and as one - third of the scheduled time was over,
so, remaining time is = 3/4 - 1/4 = 5/12
So, If the total numbers of men is Z
then ,we can write,
20×1/3×1/4 = Z×5/12×3/4
so, Z= 48
So,(48-20=28) more men should now be employed to complete the work in three-fouths of the origionally scheduled time.