Math, asked by subashrock619, 11 months ago

Two content Managers can complete developing questions for a module in 18

days .7days after they start working. 10 interns join them .How many days will

they take to complete the remaining work if they are all equally efficient?

Answers

Answered by amitnrw
50

Answer:

11/6 days    ( 2 Days)

Step-by-step explanation:

Two content Managers can complete developing questions for a module in 18

days.

=> one manager will take 18 * 2 = 36 Days to complete module

=> one manger one day work = 1/36

Work done in 7 Days =  7/18

Remaining work = 1 - 7/18  = 11/18

10 Interns join so total Man power available = 2 + 10 = 12

12 People one day work  = 12 * 1/36  = 1/3

Number of days required = (11/18)/(1/3)  = 11/6   ≈ 2 Days