Two materials x and y are used as follow:
minimum usage 50units per week, maximum usage 150 units per week each, normal usage 100 units per week each.
odering quantity(units) of x600
delivery period(weeks) of x 4 to 6
odering quantity of y 1000 units
delivery period weeks of y 2to 4
calculate minimum level,maximum level, odering level.
Answers
Answered by
8
Answer:
Search ur ques in google and
Open da link shown
in da attachment
Attachments:
Similar questions